December 30, 2022 - MERCED COUNTY – The California Department of Transportation (Caltrans) will perform various closures on Interstate 5 (I-5) and State Route 99 (SR-99) for maintenance and construction operations. Work to occur as follows;
INTERSTATE 5:
- Full closure of the John C. Erreca Rest Areas on northbound and southbound I-5 beginning Monday, April 4, 2022, through July 2023.
o ALTERNATE LOCATIONS: Motorists are advised to use either the Westley Rest Area (San Joaquin/Stanislaus County line) or the Coalinga-Avenal Rest Area (Fresno/Kings County line). Electric vehicle charging stations are available at the Westley Rest Area.
STATE ROUTE 99:
- Full off-ramp closures from northbound SR-99 at Childs Avenue for construction beginning Thursday, January 5, through Friday, January 6, 2023, from 8:00 p.m. until 5:00 a.m.
- Full on-ramp closures from Childs Avenue to southbound SR-99 for construction beginning Tuesday, January 3, through Friday, January 6, 2023, from 10:00 p.m. until 6:00 a.m.
- Long-term, full off-ramp closure from southbound SR-99 at Childs Avenue through January 10, 2023.
- Full off-ramp closure from northbound SR-99 to SR-140 East for construction beginning Tuesday, January 3, through Wednesday, January 4, 2023, from 8:00 p.m. until 5:00 a.m.
- Full on-ramp closures from SR-140 East to northbound SR-99 for construction beginning Tuesday, January 3, through Friday, January 6, 2023, from 10:00 p.m. until 6:00 a.m.
- Full on-ramp closures from SR-140 East to southbound SR-99 for construction beginning Tuesday, January 3, through Friday, January 6, 2023, from 10:00 p.m. until 6:00 a.m.
- Full off-ramp closures from southbound SR-99 at SR-140 East for construction through Wednesday, January 4, 2023.
- Full off-ramp closures from northbound SR-99 at 16th Street for construction beginning Wednesday, January 4, through Friday, January 6, 2023, from 8:00 p.m. until 5:00 a.m.
- Full on-ramp closures from 16th Street to southbound SR-99 for construction beginning Tuesday, January 3, through Friday, January 6, 2023, from 10:00 p.m. until 6:00 a.m.
- Long-term full off-ramp closure on northbound SR-99 at G Street for construction through March 24, 2023.
- Full on-ramp closure from G Street to southbound SR-99 for construction beginning Wednesday, January 4, through Friday, January 6, 2023, from 8:00 p.m. until 5:00 a.m.
- Full on-ramp closure from SR-59/Martin Luther King Jr. Way to northbound SR-99 beginning Tuesday, January 3, through Wednesday, January 4, 2023, from 8:00 p.m. until 5:00 a.m.
- Full off-ramp closures from northbound SR-99 at SR-59/Martin Luther king Jr. Way for construction beginning Tuesday, January 3, through Friday, January 6, 2023, from 10:00 p.m. until 6:00 a.m.
- Full on-ramp closures from SR-59/Martin Luther King Jr. Way to southbound SR-99 for construction beginning Tuesday, January 3, through Friday, January 6, 2023, from 8:00 p.m. until 5:00 a.m.
- Full off-ramp closures from southbound SR-99 at SR-59/Martin Luther King Jr. Way for construction beginning Tuesday, January 3, through Friday, January 6, 2023, from 10:00 p.m. until 6:00 a.m.
- Full off-ramp closures from northbound SR-99 at R Street for construction beginning Tuesday, January 3, through Friday, January 6, 2023, from 10:00 p.m. until 6:00 a.m.
- Full on-ramp closure from R Street to southbound SR-99 for construction beginning Tuesday, January 3, through Wednesday, January 4, 2023, from 9:00 p.m. until 6:00 a.m.
- Full on-ramp closure from SR-140/59 (V Street) to northbound SR-99 for construction beginning Tuesday, January 3, through Friday, January 6, 2023, from 10:00 p.m. until 6:00 a.m.
- Full off-ramp closure from southbound SR-99 at SR-140/59 (V Street) for construction beginning Tuesday, January 3, through Friday, January 6, 2023, from 8:00 p.m. until 6:00 a.m.
- Full on-ramp closure from 16th Street to northbound SR-99 for construction beginning Tuesday, January 3, through Friday, January 6, 2023, from 10:00 p.m. until 6:00 a.m.
- Full on and off-ramp closures on southbound SR-99 at 16th Street for construction beginning Tuesday, January 3, through Friday, January 6, 2023, from 8:00 p.m. until 6:00 a.m.
Motorists should expect five to 10-minute delays. Alternate routes should be taken whenever possible.
This work is scheduled to begin as listed, but is subject to change due to traffic incidents, weather, availability of equipment, and/or materials and construction related issues. For the safety of workers and other motorists, please Be Work Zone Alert.